The commercial plan you set out with.
Confirmed spend to date.
Orders raised but not yet invoiced.
Estimated cost still to come.
Where the job is really heading.
Historic reports tell you what's already happened. A cost-to-complete report tells you where the job is going — so you can act while the outcome is still in your hands.
Escalate scope changes, review procurement, reforecast labour and manage client expectations before the margin disappears.
On actual cost alone, this job looks like it has £80,000 of room left.
Committed and remaining cost turn an £80k cushion into a £30,000 overrun — visible now, while there is still time to act.
Straight answers, no jargon.
Contact us and we'll show forward-looking cost control on your jobs.