Bill of materials (BOM)

A bill of materials, or BOM, is a structured list of the materials, components and quantities needed to complete a job, batch or product. In job costing, it forms the basis for material cost budgeting and purchase planning.

Comparing planned BOM quantities and costs with actual consumption is how manufacturers and engineers identify material cost variance.

In a sentence
Planned materials list
Basis for material budget
Compare to actual usage
Example

BOM vs actual — where material variance comes from

A manufacturing job has a BOM specifying 200kg of steel at £4 per kg — £800 budgeted. Actual usage comes to 230kg at £4.20 per kg — £966.

The BOM gives the reference point. Job costing shows the variance: £166, split between more material used and a higher price paid. Without the BOM, the overrun is invisible.

In job costing

BOM feeds committed and actual cost

When materials from the BOM are ordered, they become committed cost on the job. When they arrive and are used, they become actual cost. The BOM is the reference point that keeps material budgeting meaningful.

FAQs

Questions, answered

Straight answers, no jargon.

Usually the estimator, engineer or production planner before the job starts, based on drawings, specifications and quantities. The BOM then serves as both the purchasing guide and the material budget baseline.
It can. Design revisions, engineering changes or material substitutions may update what's needed. A revised BOM should flow through to the job budget so material variances stay meaningful.
No. Construction uses BOMs for fabricated elements; civil engineering uses them for groundwork and structural materials; trades use them for standard equipment kits. Anywhere a job needs predictable material quantities, a BOM adds structure and control.