A manufacturing job has a BOM specifying 200kg of steel at £4 per kg — £800 budgeted. Actual usage comes to 230kg at £4.20 per kg — £966.
The BOM gives the reference point. Job costing shows the variance: £166, split between more material used and a higher price paid. Without the BOM, the overrun is invisible.
When materials from the BOM are ordered, they become committed cost on the job. When they arrive and are used, they become actual cost. The BOM is the reference point that keeps material budgeting meaningful.