Budget variance

Budget variance is the difference between the planned cost (or revenue) on a job and the actual cost (or revenue) recorded. A negative variance means costs are above budget; a positive variance means they're below.

Budget variance analysis is how project teams understand which costs ran over, by how much, and why — and how future estimates should change as a result.

In a sentence
Planned vs actual gap
Positive or negative
Explains where a job moved
Example

Knowing where the overrun happened

A job is £18,000 over budget at completion. Without variance analysis, the question is 'how?'. With it: labour was £11,000 over due to rework, materials were £4,000 over due to a price increase, and subcontractors were £3,000 over due to an unapproved variation.

Each cause has a different fix — quoting assumption, procurement, variation management. Variance analysis points to the right one.

Why it matters

Variance improves the next quote

If overruns on a particular cost category (labour, materials, subcontractors) repeat across jobs, the estimate structure needs to change. Budget variance analysis by cost code, over multiple jobs, is how pricing gets more accurate over time.

FAQs

Questions, answered

Straight answers, no jargon.

Not necessarily. A positive variance (cost below budget) might mean delivery is ahead of schedule, but it could also mean costs haven't been fully captured yet, or that some planned work hasn't happened. Check the completeness of the cost record before concluding.
Focus on significant variances first — particularly those that repeat across jobs in the same cost category. A small one-off variance is usually noise. A systematic overrun in labour or materials on a particular job type signals a structural estimating problem.
Monthly at minimum on active jobs, ideally at each milestone or cost code review. End-of-job variance tells you what happened; mid-job variance gives you time to respond.