A job has a £20,000 materials budget. Invoices show £8,000 of actual cost, so an actual-only report suggests £12,000 remains.
But the project manager has raised £9,000 of purchase orders. The real remaining budget before any further spend is £3,000 — and only committed cost shows that.
If a job only shows actual cost, the warning comes when invoices arrive — after the commercial decision that caused the overrun. Committed cost moves that warning forward, so project managers, finance and directors can respond in time.