Committed cost is money the business has already agreed to spend on a job — purchase orders, subcontractor instructions, approved quotes or ordered materials — even though the invoice hasn't arrived yet.

It gives a more realistic view of a job than actual cost alone, because spend that's been ordered has effectively already used part of the budget.

In a sentence
Agreed but not yet invoiced
Earlier than actual cost
Shows true remaining budget
Example

Why it changes the picture

A job has a £20,000 materials budget. Invoices show £8,000 of actual cost, so an actual-only report suggests £12,000 remains.

But the project manager has raised £9,000 of purchase orders. The real remaining budget before any further spend is £3,000 — and only committed cost shows that.

Why it matters

It lets teams act earlier

If a job only shows actual cost, the warning comes when invoices arrive — after the commercial decision that caused the overrun. Committed cost moves that warning forward, so project managers, finance and directors can respond in time.

FAQs

Questions, answered

Straight answers, no jargon.

When the business agrees to spend it — a purchase order raised, a subcontract signed, a quote accepted. You don't need to wait for an invoice. The commitment is the decision, not the bill.
Not usually. It's a management control concept, not an accounting entry. It's visible in the job costing system before it posts to your accounting software when the invoice is processed.
If a purchase order is cancelled or a subcontract changes, the committed amount should be updated or removed. Accurate committed cost depends on keeping commitments up to date as jobs move.