Cost-to-complete

Cost-to-complete is the estimated cost still required to finish a job — a forward-looking number that shows what remains, not just what's been spent.

Combined with actual and committed cost, it gives the expected final cost and margin.

In a sentence
The cost still to come
Forward-looking
Reveals the final position
Example

Where a job will finish

A job has £60,000 actual cost, £20,000 committed and £25,000 of remaining cost-to-complete. Expected final cost is £105,000.

If the budget was £100,000, the job is forecast to finish £5,000 over — visible now, while there's still time to act.

Why it matters

Actual cost alone can mislead

A job can look healthy on actual cost yet finish badly if the remaining work is expensive. Cost-to-complete is what flags that risk before completion.

FAQs

Questions, answered

Straight answers, no jargon.

Usually the project manager or quantity surveyor, based on remaining scope and agreed rates. The job costing system can pre-populate a starting estimate from the original budget, adjusted for the work already done.
At least monthly on active jobs — or at each major milestone. Jobs change: scope varies, delivery runs faster or slower, prices shift. An outdated estimate is as misleading as no estimate.
Cost-to-complete is the remaining spend still to come. Expected final cost (or cost at completion) is the total: actual cost plus committed cost plus cost-to-complete combined.