A job has £60,000 actual cost, £20,000 committed and £25,000 of remaining cost-to-complete. Expected final cost is £105,000.
If the budget was £100,000, the job is forecast to finish £5,000 over — visible now, while there's still time to act.
A job can look healthy on actual cost yet finish badly if the remaining work is expensive. Cost-to-complete is what flags that risk before completion.