Forecast margin is the expected profit margin on a job when it finishes, based on cost and revenue data available today. It combines actual cost already recorded, committed cost already agreed and estimated remaining cost still to come.

Forecast margin is more useful than current margin because it shows where a job is heading, not just where it has been.

In a sentence
The expected final result
Actual + committed + remaining
Changes as the job moves
Example

A job that looks fine — until you forecast it

A job is halfway through. Actual cost is £60,000, revenue billed is £90,000. The current margin looks comfortable.

But remaining cost is estimated at £80,000, and there is £20,000 of committed cost not yet invoiced. Forecast final cost is £160,000 against a revenue budget of £175,000. Forecast margin is 8.6% — below the 15% target. The team now knows to act.

Why it matters

Forecast margin is what lets you intervene

Current margin tells you the historical position. Forecast margin tells you the likely final result. That's the difference between a report and a management tool.

FAQs

Questions, answered

Straight answers, no jargon.

Current margin shows the position based on cost and revenue recorded so far. Forecast margin adds committed cost and an estimate of remaining work to project the final result — it changes as the job progresses.
Actual cost already recorded, committed cost agreed but not yet invoiced, and a cost-to-complete estimate for remaining work. Without all three, the forecast is incomplete and potentially misleading.
Investigate the cause before acting. Is it a cost overrun? Unrecovered variations? A pricing assumption that was wrong? Each cause points to a different response: cost control, raising a variation order, or adjusting how similar work is priced in future.