A job budgeted 80 hours of engineer time at £35 per hour — £2,800. The actual time recorded was 95 hours at £38 per hour (overtime uplift). Actual labour cost was £3,610.
Labour variance: £810 over. The cause: 15 more hours than expected, compounded by a higher effective rate. Knowing both means you can price the risk next time — or manage the hours before the job closes.
If labour consistently runs over budget on a particular type of work, the estimate is wrong — not the delivery team. Reviewing labour variance by job type, over time, is how labour assumptions get more accurate.