A job budgets 100 units of material at £5 per unit — £500. Actual: 112 units at £5.40 per unit — £604.80.
Total variance: £104.80 over. Usage variance: 12 extra units at the budgeted rate (£60). Price variance: all 112 units at £0.40 more (£44.80). Separating the two shows whether to address waste and over-ordering (usage) or supplier pricing and procurement (price).
Systematic material overruns on the same items suggest the estimate rate needs updating, or waste on site needs addressing. Variance by material category, over multiple jobs, is how material cost assumptions improve.