A contractor has completed £80,000 of work on a £200,000 contract. So far, only £60,000 has been invoiced. The £20,000 gap is WIP — revenue earned but not yet recognised.
Reporting without WIP makes the business look less profitable than it is. Including it gives a fairer picture of where income actually stands.
Calculating WIP accurately depends on knowing how much of a contract is complete. That requires reliable cost data — labour booked, materials consumed, subcontractors instructed. Live job costing makes that calculation faster and more defensible.