What you expected to spend when you quoted or budgeted the job.
Spend already ordered, instructed or agreed — before the invoice lands.
Costs already recorded: invoices, posted time, expenses, supplier bills.
Actual + committed + remaining, so you see where the job is heading.
A £100,000 job that looks like it still has £40,000 of room left.
Purchase orders and subcontract instructions have already eaten the budget — visible now only if committed cost is on the report.
A basic report says: budget £50,000, actual £32,000, remaining £18,000 — and looks comfortable.
A better report adds committed cost of £14,000, so the true remaining budget before any further work is £4,000. That second view creates a very different management conversation, and it's the one that protects margin.