What's already recorded against the job.
Ordered or instructed, but not yet invoiced.
The estimate of what's still needed to finish.
Actual + committed + remaining — the figure that matters.
Actual cost alone suggests this £100,000 job is comfortable.
Expected final cost = actual + committed + remaining. The £5k overrun is visible now, while there's still time to act.
A job looks healthy when the report only shows actual cost — usually because invoices arrive late, purchase orders aren't included, or remaining work is underestimated.
Cost-to-complete prevents that false confidence by combining what's spent, what's committed and what's still to come.